Enjoy Upto 50% OFF on Assignment Solutions!
Ph.D. Writers For Best Assistance
Plagiarism Free
No AI Generated Content
Need an Assignment Helper in the UK? Native Assignment Help is here to support you every step of the way. Our skilled experts specialize in a wide range of subjects and are committed to delivering high-quality assignments that meet the highest academic standards.
Project Management can be referred to the use of tools and techniques, skills, and knowledge to deliver something valuable to people. Working on a project is not easy for an organization as it sounds. Every project has different requirements and the project manager needs to apply different methods, skills to fulfill the same. This report is based on a project on food processing.
The report will be divided into three parts. In PART-A, the background of this project, and the project management techniques which will be used for managing the development of the product i.e., an energy drink. The steps the project manager will need to take for improving the term-to-market of this new product will be discussed. Quality management and its key steps will be discussed along with management of project confidentiality. The report will also include the identification of key measures which can be applied to develop a new approach to communication. At the end of Part-A, the benefits of this new communication approach will be discussed for consumers. Part-B will include a Gantt Chart to demonstrate the project planning. Part-C will be a discussion about the budget of product development.
This food processing project will be focused on the development of an energy drink. Nowadays, people are so busy in their fast life, especially in metro cities. In this kind of environment, the stress level of people especially the youngsters is becoming high by the time. Producing an energy drink that will help to lower this stress of people will be the aim of this project. The drink will also help reduce body fat as it will be made up of all-natural ingredients and no preservatives will be added.
Mental health issues like anxiety, stress have become common in the past few years. Plus, people generally do not share these issues. This energy drink will help them to keep their mind calm and cool, release stress and anxiety. The product development that is the development of energy drink on which the project is based is aimed to satisfy the current needs of consumers regarding health and fitness. The project managers will develop this drink through this project in a way that it will get developed with minimal cost and will be sold to customers at an average price initially. The project managers, with the aim of product development, also need to develop promotional strategies to launch this drink successfully.
To develop this energy drink and launch it successfully, the project manager needs to evaluate different project management techniques and pick the suitable one (Akhtar and Eniodunmo, 2021). The finalized project management technique should be the one that becomes the evidence of the quality of the project to attract investors. The following project management techniques are available among which the project manager choose one for this food processing project:
PERT
It is known as Program Evaluation and Regulation Technique. PERT falls under the Agile methodology of project management. PERT if will be applied to this food processing project, it will mainly be helpful to manage the budget and time aspect. It is because PERT allows to break down the whole project into smaller detailed tasks and then, identifies the dependency of these tasks on one another (Cheng et al, 2020). If the project manager will use this technique, a PERT chart will need to be defined and represented to every member of the project team. The PERT chart includes all the activities with an allotted duration to the same.
Figure 1: Program Evaluation and Review Technique
Source: Rajpara 2021
This project technique is mainly useful for complex and large projects which involve a large number of activities and tasks. The project involves mostly non-routine tasks that can be managed well with the PERT technique of project management.
PMBOK
It is also known as PMI which is a project management institute. This project management technique is named on the basis of the institute name. PMI or PMBOK is a non-profit organization that has developed this technique in which six stages of project management have been defined. PMBOK- the project management body of knowledge has defined the six phases of project management as a whole technique for managing the projects (Frederico 2021). The categorization of a project to manage it well should be into 5 areas according to this technique. These areas/phases include initiation, the definition of the project, its designing phase, the project development, implementation of the same, and closing phase of the project which also includes follow-up.
Figure 2: Project Management according to PMBOK Technique
Source: Rajpara 2021
PMBOK technique of project management can be used for any type and size of the project. It is because every project goes through the stages defined above. If the project manager of this food processing project will choose to use the PMBOK technique to develop the energy drink, it will be helpful to share the same vision with the whole project team and the shareholders as well.
Waterfall
This is a classic technique of project management that ensures effective planning of the project and the implementation of the basics of project management. If the project manager will apple Waterfall for developing the energy drink and to manage this whole food processing project, a sequence of activities will need to be set. The waterfall technique does not allow scope for many changes as it defines a systematic flow of project activities (Nurdiansyah and Wijayanto, 2018). This technique helps to plan the whole project lifecycle step-by-step. With this technique, the project manager will be able to show the progress of the development of the energy drink consistently.
Figure 3: Waterfall project management technique
Source:Rajpara 2021
This project management technique is most suitable for projects which need to be carefully planned and executed. Mainly, the projects with less clarity need the application of the Waterfall technique to manage it. To apply this technique, proper planning is required and closure of every stage is a must.
After evaluation of the above-discussed technique, it can be said that the PMBOK technique will be best suited for this food processing project. The project manager will use the phases of project management given by PMI for product development i.e., the development of energy drinks.
Marketing of the Energy Drink
The energy drink will be mainly produced and launched through this project in the market of UK. The targeted customers for this energy drink will be the age group of 15 to 35 within the United Kingdom. The project manager has taken a crucial step of creating a marketing mix of this product- the energy drink to ensure clarity over this area (Sudari et al, 2019).
Product- It is the energy drink that will be developed through the project with an aim to serve the customers engaged in a highly busy routine. The drink will be made up of all-natural ingredients and will help reduce weight, release stress, and keep the mind cool. The drink will be produced and available in three different flavors initially.
Price- For each drink, the price initially will be kept as 6 euros for a half-liter bottle and 12 euros for a one-liter bottle. The combos of drinks will also be created and discounts will be given to consumers. Like, a combo of three one-liter bottles of three different flavors will be priced at 30 euros.
Place- The drink will be mainly marketed and launched within the United Kingdom. The people of the UK who fall under the age group of 15 to 35 will be targeted to sell the drink.
Promotion- For promoting the energy drink or for its marketing, different strategies will be used. These include advertising through offline and online mediums including social media channels. Other marketing and promotional strategies will be used like direct marketing in which the sellers go to the doorsteps of people and promote this drink (Zia 2017). To promote the energy drink more, discounts and coupons may also be used to attract customers. Deciding the promotional strategy will be one of the main aspects of marketing.
Launch of the Energy Drink
Once the drink will be promoted well, the step to launch it will need to be taken. The drink will be launched after one month of continuous promotion and marketing. On the launch day, the first 50 customers will get free energy drink bottles. These free drinks will be given on a basis first come first serve basis.
As this is a food processing project, for the development of an energy drink which will remain unique within the market, the project manager will need to ensure producing a high-quality energy drink (Akhmetova and Suleimenova, 2018). To ensure quality while managing this project, the project manager will need to take the following steps:
To ensure confidentiality throughout the process of this food processing project, the project manager will need to focus on the following elements:
An approach will be developed by the project manager to reduce the communication problems within this food processing project. There are many measures available to reduce communication issues. Among various options, one effective and relevant approach needs to be implemented by the project manager.
For this project, the new approach for communication will be RACI charts. It refers to being responsible, accountable, consulted, and informed (Suhanda and Pratami, 2021). This approach will allow the project team members to become more responsible towards their tasks to develop the product- the energy drink. Also, this will help to make the team members more accountable for their project responsibilities. The approach will be helpful to consult the project relevant information better and to make more effective decisions. This approach will also be significant to keep everyone informed regarding project decisions. Applying RACI in this food processing project will not just help to make communication better but will also be helpful in reducing the elements hindering communication. Many unnecessary elements need to be cut out to reduce communication problems within the team members and with external parties as well like consumers, investors, etc. A new approach like RACI will help do so.
The timeline for the whole process of launching the energy drink is 20 months long. The final product would have to undergo various processes as listed above. The market research would take about 2 months wherein surveys of potential users would be taken and trends would be determined. Based on the market research, product development would be done. This would take 3 months and process & capacity design would take 3 months. After this, the setting up the supply chain for raw material and services related to the energy drink would take about 5 months of time as this requires procurement which is quite time-consuming. Job design and human resource would take 3 months and finally the product launch and marketing would take 2 months.
Figure 1: Budget
Source: By Author 2021
A budget of a total of 50,000 euros will be required to complete the production of energy drinks successfully. In the first phase of project management i.e., initiation, the manager will require 2000 euros for planning the activities. Also, a project charter will be required in which the project manager will list every minor detail relevant to the project including project objectives, scope, stakeholders, available resources, identified risks, milestones, risk mitigation strategies, and so on. The second phase i.e., projectdefinition in which the project manager will conduct meetings with the stakeholders to plan further things in which venue and caterings will be finalized (Nguyen, Nguyen, and Pham, 2019). This is why there is a requisite of 1000 euros in the third phase of this food processing project. In the designingphase, the project manager will be needed 16000 euros for designing a product in which the packaging, labeling, logo, and tagline will be decided. The development phase is also essential because the project manager will be focused on many activities before implementing the project. These activities include market research, product development, setting the price of a product, and so on. So, the manager will be needed 21500 euros to manage the same. Execution, Monitoring and controlling, and moving to the production are included in the phase of project implementation which will be required 9000 euros. At this stage, promotional strategies will be used by the manager for the promotion of the product. The last stage is related to closing and follow-up in which the project manager will be needed only 500 euros for preparing the closing documents of the project.
Conclusion
It can be concluded from the report that the food processing project will be focused upon the development of the energy drink. The report has identified that the available project management techniques include PERT, PMBOK, and waterfall among which the project manager has chosen the PMBOK technique to manage this food processing project. In regards to the marketing aspect of this project, the manager has developed the marketing mix and decided on the launch of the product as well. Regarding quality management, it has been identified that seven major steps need to be followed including quality control. To ensure confidentiality, it has been identified that the project manager needs to encrypt the files, follow confidentiality, manage data access, etc. It has also been identified that the RACI approach will be needed to get implemented for reducing communication issues. In regards to budget, it has been identified that 50,000 euros will be the total budget to develop and launch the energy drink.
Akhmetova, S. and Suleimenova, M., 2018. Quality management system for improvement of quality and efficiency of food production: case of dairy products enterprise. Entrepreneurship and Sustainability Issues, 6(1), pp.289-310.
Akhtar, M.N. and Eniodunmo, K.O., 2021. Examination of Strategic Management Accounting Techniques among SMEs (Perception of the Usefulness, Adoption, and Outcomes): A multiple Case Study of SMEs in the Food Processing Industry in Nigeria.
Cheng, F., Lin, M., Yüksel, S., Dinçer, H. and Kalkavan, H., 2020. A hybrid hesitant 2-tuple IVSF decision-making approach to analyze PERT-based critical paths of the new service development process for renewable energy investment projects. IEEE Access, 9, pp.3947-3969.
Deepa, N. and Pandiaraja, P., 2021. E health care data privacy preserving efficient file retrieval from the cloud service provider using attribute based file encryption. Journal of Ambient Intelligence and Humanized Computing, 12(5), pp.4877-4887.
Dooley, D.M., Griffiths, E.J., Gosal, G.S., Buttigieg, P.L., Hoehndorf, R., Lange, M.C., Schriml, L.M., Brinkman, F.S. and Hsiao, W.W., 2018. FoodOn: a harmonized food ontology to increase global food traceability, quality control and data integration. npj Science of Food, 2(1), pp.1-10.
Frederico, G.F., 2021. Project Management for Supply Chains 4.0: A conceptual framework proposal based on PMBOK methodology. Operations Management Research, pp.1-17.
Nguyen, N., Nguyen, T. and Pham, D., 2019. Factors affecting the responsibility accounting in Vietnamese firms: A case study for livestock food processing enterprises. Management Science Letters, 9(9), pp.1349-1360.
Nurdiansyah, Y. and Wijayanto, F., 2018. The design of e-commerce system in the shrimp paste industry using the method of Structured Analysis and Design Technique (SADT) to increase marketing. In MATEC Web of Conferences (Vol. 164, p. 01049). EDP Sciences.
Sudari, S., Tarofder, A., Khatibi, A. and Tham, J., 2019. Measuring the critical effect of marketing mix on customer loyalty through customer satisfaction in food and beverage products. Management Science Letters, 9(9), pp.1385-1396.
Suhanda, R.D.P. and Pratami, D., 2021. RACI Matrix Design for Managing Stakeholders in Project Case Study of PT. XYZ. International Journal of Innovation in Enterprise System, 5(02), pp.122-133.
Woodhouse, A., Davis, J., Pénicaud, C. and Östergren, K., 2018. Sustainability checklist in support of the design of food processing. Sustainable Production and Consumption, 16, pp.110-120.
Zia, M., 2017. Impact of product attributes on purchase decision: a study of processed food consumer in India. Publication name, p.42.
Go Through the Best and FREE Samples Written by Our Academic Experts!
Native Assignment Help. (2024). Retrieved from:
https://www.nativeassignmenthelp.co.uk/project-planning-and-management-health-care-industry-sample-10958
Native Assignment Help, (2024),
https://www.nativeassignmenthelp.co.uk/project-planning-and-management-health-care-industry-sample-10958
Native Assignment Help (2024) [Online]. Retrieved from:
https://www.nativeassignmenthelp.co.uk/project-planning-and-management-health-care-industry-sample-10958
Native Assignment Help. (Native Assignment Help, 2024)
https://www.nativeassignmenthelp.co.uk/project-planning-and-management-health-care-industry-sample-10958
Equality and Diversity at Sainsbury's: A Case Study on Workplace...View or download
Impacts Of Facilities Management 1. Introduction: Impacts Of Facilities...View or download
Vivian Frimpong's Employability and Career Development Plan Assignment...View or download
Marketing Management Assignment Sample Introduction: Walmart is a retail...View or download
Law of Obligations Assignment Introduction: Law of Obligations...View or download
Queen of the South: Netflix's Drug Cartel Drama Analyzed Through Crime...View or download
Get your doubts & queries resolved anytime, anywhere.
Receive your order within the given deadline.
Get original assignments written from scratch.
Highly-qualified writers with unmatched writing skills.
We utilize cookies to customize your experience. By remaining on our website, you accept our use of cookies. View Detail
Hi! We're here to answer your questions! Send us message, and we'll reply via WhatsApp
Please enter a messagePleae enter your phone number and we'll contact you shortly via Whatsapp
We will contact with you as soon as possible on whatsapp.
Ph.D. Writers For Best Assistance
Plagiarism Free
No AI Generated Content
offer valid for limited time only*